Air Dome Heating Comparison for DACH: Germany, Austria, and Switzerland

Air-supported structure for the DACH comparison of heating systems and regulations

Short Answer: The same air-supported hall can be treated differently under the law in Germany, Austria, and Switzerland. Germany explicitly exempts air-supported halls in its current Building Modernisation Act—formerly the GEG—with the exception of §§ 74 to 78. Austria prohibits fossil-fuel-operable heating systems for new structures but does not explicitly classify air domes in the EWG. In Switzerland, cantonal law is decisive; the MuKEn 2025 are only model regulations. Therefore, first select the site and legal pathway, then calculate the heating load, and only then compare permissible systems.

A heating system for an air dome in the DACH region is not selected based on output and energy price alone. The heat generator must cover the winter load, work in concert with the warm air distribution and hall operations, be connectable at the site, and comply with the applicable local regulations. This last point is especially crucial for cross-border projects.

Germany, Austria, and Switzerland follow different regulatory models. In Germany, federal law contains an explicit exemption for air-supported halls. In Austria, much depends on the legal classification as a 'new structure'. In Switzerland, there is no single energy law identical for all cantons. Consequently, a heating option that can generally be considered openly in Germany may require additional proof, a different heat source, or an official exemption in Austria or a Swiss canton.

For municipalities, tennis clubs, and operators of outdoor and indoor swimming pools, the practical question is therefore not just 'Which heating system is efficient?' but rather: What is the best air dome heating solution that is permittable at the specific site, technically robust, and economical over its planned service life? This is precisely the search and decision-making intent that the following comparison addresses.

This article is a planning guide, not legal advice and not a project-specific HVAC design. Before ordering, submitting a building application, or beginning installation, the current legal situation, project classification, and technical design for the specific site must be confirmed in writing.

Table of Contents

DACH Comparison: What Differentiates the Three Countries?

The biggest difference lies not in the warm-air technology, but in the legal starting point. The following table illustrates the planning logic. It does not replace a site-specific assessment.

Country Key Energy Law Basis Treatment of Air-Supported Halls Implication for System Choice First Secure Step
Germany Building Modernisation Act (GModG), formerly the Building Energy Act (GEG) § 2 para. 2 no. 5 explicitly exempts air-supported halls and tents; §§ 74 to 78 remain excluded The general heating requirements of the Act do not apply directly to an air-supported hall classified as such; other regulations may still apply Clarify classification as an air-supported hall as well as building, fire, immission control, and connection rules
Austria Renewable Heat Act (EWG) plus state building and procedural law The EWG does not mention air-supported halls; the classification as a new structure is a key factor If § 3 EWG applies, systems operable with fossil fuels and non-quality-assured district heating are generally not permitted Obtain written project classification before selecting or ordering the heat source
Switzerland Cantonal energy and building law; MuKEn as a model; EnFK recommendation EN-132 No identical rule for all cantons; implementation and enforcement differ Renewable heat, suitable heating networks, and EN-132 requirements can be key; the cantonal version is binding Determine the canton, municipality, and submission date, then check the applicable law and the energy agency

No one-size-fits-all DACH solution: The terms 'temporary', 'mobile', or 'seasonal' do not automatically create an energy law exemption in either Austria or Switzerland. Even in Germany, the explicit exemption requires that the specific project is actually treated as an air-supported hall in legal terms. Building, fire, noise, emissions, and utility regulations must still be assessed separately.

Germany: The GModG Exemption for Air-Supported Halls

As of August 2026, the former Building Energy Act is now the Building Modernisation Act (GModG). The amending act was promulgated on 28 July 2026 and came into force on 29 July 2026. For many searching online, 'GEG air dome' remains the familiar term, but the legally current name is GModG.

§ 2 para. 2 no. 5 GModG continues to stipulate that the Act, with the exception of §§ 74 to 78, does not apply to air-supported halls and tents. The general requirements for heat supply therefore do not directly apply to a correspondingly classified air-supported hall under this Act.

The exemption is clear, but it is not a blanket operating permit for any heating device. The following points in particular must still be checked:

This makes the technical selection for air dome heating systems Germany comparatively open. Gas, heat pumps, heating networks, biomass, or other suitable heat sources can be considered. Nevertheless, the lowest initial investment should not automatically win. Energy price risk, emissions, maintenance, connection capacity, and expected service life all belong in the same life-cycle comparison.

More details can be found in our country guide Heating for Air Domes in Germany.

Austria: The EWG Makes Classification Decisive

Austria has no explicit exemption for air-supported halls in the EWG comparable to Germany's. According to § 3 EWG, for new structures, the installation of heat supply systems that can be operated with fossil fuels is not permitted. Connection to district heating that is not quality-assured is also not permitted.

§ 2 defines 'new structures' via new buildings and certain reconstructions. However, the Act does not mention air-supported halls. Whether a seasonally installed hall—with its anchoring, use, period of installation, and remaining infrastructure—falls under this definition cannot, therefore, be inferred from the word 'temporary' alone.

What does 'quality-assured district heating' mean?

The Austrian definition requires more than just an available connection. It necessitates sufficient capacity and volume, a regulated price adjustment mechanism, and specifications regarding the heat source or decarbonisation. Under the current version, the heat must either originate at least 80 percent from renewable energy sources, high-efficiency cogeneration, waste heat, or a combination thereof, or the network must meet a binding decarbonisation plan that ensures permanent compliance with these criteria from 2035 onwards and does not provide for any expansion of fossil-fuel plant capacity.

An advertising claim from the utility or the general term 'district heating' is therefore not sufficient. Written confirmation of the capacity, price regulation, energy mix, or decarbonisation plan is required for the project file.

Which systems are robust starting points for sports hall heating Austria?

As long as the classification is not clarified, heat pumps, suitable biomass, quality-assured district heating, and usable waste heat are the more cautious initial options. A direct electric solution may seem technically simple, but for large halls, it may require very high connection capacity and can lead to high demand charges and operating costs. Gas or oil technology should not be ordered before the authority has confirmed the classification and permissibility in writing.

The complete guide to authorities and systems can be found at Heating for Air Domes in Austria.

Switzerland: MuKEn are a Model, the Canton is Decisive

In Switzerland, there is no single, nationwide identical answer for every heated inflatable structure. The cantons are primarily responsible for the energy consumption of buildings. The EnDK coordinates common model provisions with the MuKEn; they only become binding through cantonal implementation.

The MuKEn 2025, adopted on 29 August 2025, recommend a current regulatory model to the cantons. In the model, this includes renewable heat or otherwise unusable waste heat for new buildings, restrictions on electric resistance heaters, and criteria for heating networks or fossil-fuel peak loads. However, these model articles are not a nationwide permit or a nationwide ban. Depending on the canton, a project may be assessed under an earlier implementation, already under new rules, or during a transitional phase.

What role does EN-132 play?

The EnFK recommendation EN-132 deals with heated air-supported halls and the assessment of corresponding exemption permits. It specifies, among other things, a suitable multi-layer membrane structure, airtightness at anchorages and penetrations, airlocks, controlled ventilation, consumption metering, as well as sustainable air dome heating or otherwise unusable waste heat. EN-132 is not in itself a nationwide law, but it can become relevant through cantonal reference or in enforcement.

Nidwalden is a documented example: The cantonal energy ordinance explicitly refers to EN-132 for heated air-supported halls and requires renewable energy or otherwise unusable waste heat. This rule cannot be transferred to Zurich, Bern, Basel, or any other canton without checking its current regulations.

Further details on inflatable structure heating Switzerland are available in the guide Heating for Air Domes in Switzerland.

Air Dome Heating Systems: A Country-by-Country Comparison

Heat is often distributed via air, but the heat source can vary. For example, a heat pump, heating network, boiler, biomass, or waste heat can supply a heating coil in the air handling unit. Pressurisation, fresh air, recirculation, and heating work together but are not the same function.

Heating Option Technical Assessment Germany Austria Switzerland
Heat Pump Performance and efficiency at design temperature, defrosting, flow temperature, noise, power connection, and peak load Assess technically and economically; GModG exemption does not replace site permits Fossil-free starting point; confirm installation, noise, connection, and peak load separately Often a suitable starting point; check cantonal rules, noise, and any drilling or water permits
Heating or District Heating Network Capacity, flow and return temperatures, routing, connection costs, basic and demand charges, proof of origin Check local ordinances and contractual conditions If the EWG applies, the district heating must be quality-assured Check cantonal requirements and heat mix; do not apply MuKEn model values without verification
Biomass Storage, delivery, conveying, buffer, partial load, ash, chimney, emissions, and maintenance Generally an option to consider; observe fire, emissions, and storage regulations Renewable starting point, but the system and procedure still require assessment for permitting Check cantonal air pollution control, fire, and energy regulations
Gas or Oil Supply, fuel storage, flue gas, emissions, price and CO₂ risk Not automatically prohibited by the GModG exemption; other rules still apply Generally not permitted if classified as a new structure and the system can be operated with fossil fuels No general nationwide statement; check cantonal legal situation and any possible exemptions
Direct Electric Heating Very high connection capacity, demand tariff, operating costs, and grid capacity Note GModG exemption, but electrical and connection rules still apply Fossil-free at the unit; assess technical and economic viability and other regulations Restricted depending on cantonal implementation; the MuKEn 2025 model provides for a general ban on fixed resistance heaters with regulated exceptions
Waste Heat / Hybrid Availability, temperature level, backup, property line, control, and share of peak load Assess technically and contractually Check any additional fossil-fuel-operable system against the EWG classification Rules for peak load and waste heat depend on the canton; MuKEn values are not automatically applicable law

Planning Principle: The seasonal performance factor of a heat pump, the efficiency of a boiler, or the unit price of a heating network are not the sole deciding factors. For an air-supported hall, what counts is whether the overall system provides the required heat at the local design temperature, at the necessary heat-up speed, and with the actual air exchange rate. This is key to air dome energy efficiency DACH.

The DACH Decision in Six Steps

  1. 1. Determine the site first: Specify the country, state or canton, municipality, plot, installation period, and submission date. Without a site, a reliable legal review is impossible.
  2. 2. Describe the project clearly: Document the use, hall dimensions, membrane structure, anchoring, foundations, permanently remaining parts, number of occupants, and ancillary buildings.
  3. 3. Clarify the legal pathway in writing: Ask the responsible building and energy authority about the classification, procedure, required proofs, and possible reliefs. The EWG classification in Austria, the cantonal legal situation in Switzerland, and the classification as an air-supported hall in Germany are central.
  4. 4. Calculate the heating load and air system: Consider the outdoor climate, setpoint temperature, envelope area, U-values, airtightness, fresh air, door openings, occupancy, internal gains, and heat-up mode.
  5. 5. Confirm the infrastructure: The grid operator or heat supplier must confirm the capacity, tariff, routing, origin, and connection time in writing. A technical idea without available capacity is not a viable option.
  6. 6. Economically compare only permissible options: Calculate investment, connection, energy, demand charges, maintenance, replacement, personnel, emissions, and price risk over the same period.

This sequence prevents a common mistake: selecting a heating unit first and then trying to make the permit and connection capacity fit. It is safer to first define the legally and infrastructurally possible corridors.

Fairly Comparing Air Dome Heating Costs and Operating Expenses

A sound DACH decision uses the same project and climate data for all options. Flat-rate costs per square metre or per hour, often cited in preliminary discussions about air dome heating costs Germany, are not transferable without the hall geometry, site weather, setpoint temperature, and tariff structure.

Simplified Structure:

Useful heat demand = Transmission losses + Air exchange losses + Heat-up energy − creditable internal gains

Operating costs = Energy consumption + Demand/basic charges + Auxiliary power + Maintenance + Inspections + Fuel logistics

At least three scenarios are useful: a typical weather year, a cold winter, and energy price sensitivity. For heat pumps, the performance at low outdoor temperatures is more important than a brochure value at mild conditions. For district heating, basic and demand charges can alter a pure unit-price analysis. For biomass, storage, delivery, ash, and operation must be included in the calculation. For direct electricity, the demand charge can be decisive.

The envelope and operation of the air dome affect every heat source. Airtight connections, functioning airlocks, appropriate fresh air volumes, clean filters, coordinated pressure control, and time-dependent temperature management reduce demand regardless of the country. However, savings should only be promised based on a project-specific calculation or measured, weather-normalised operational data.

What documents are needed for a preliminary inquiry?

A common data package facilitates coordination with authorities, planners, grid operators, and suppliers:

For general permit planning, our article on planning permission for air domes is also helpful. However, the project-specific list of required documents is always determined by the competent authority.

Seven Common Mistakes in Cross-Border Projects

  1. Copying the German model: The explicit GModG exemption is incorrectly applied to Austria or Switzerland.
  2. Equating 'temporary' with 'exempt': Seasonal dismantling does not replace the need for a formal project classification.
  3. Treating MuKEn as federal law: The applicable cantonal law in Switzerland is not being checked.
  4. Assuming any district heating is permissible: Austria requires quality-assured district heating for EWG compliance; in Switzerland, the cantonal implementation is the deciding factor.
  5. Focusing only on the heat generator: The air distribution, pressure maintenance, connected load, heat-up scenario, and control system are overlooked.
  6. Using performance data from mild weather: Winter performance, defrosting capabilities, and system temperatures are not verified.
  7. Ordering before receiving written confirmation: Verbal information or a manufacturer's assumption is mistaken for an official regulatory decision.

Frequently Asked Questions

Do the same rules apply in all three DACH countries?

No. Germany provides an explicit legal exemption, Austria links the EWG to a project's classification as a new building, and Switzerland regulates building energy primarily at the cantonal level.

Is the German GEG still in effect?

The law was renamed the Building Modernisation Act (GModG) and amended on 29 July 2026. The familiar search term GEG remains in common use, but GModG is the legally current act. The exemption for air-supported structures is still found in § 2 para. 2 no. 5.

Is gas heating permitted in Germany but banned in Austria?

It's not that simple. In Germany, the GModG does not apply to a correspondingly classified air-supported structure—with the exception of §§ 74 to 78; however, other regulations may still restrict the use of gas. In Austria, a system that can be operated with fossil fuels is generally not permitted for a new building under § 3 EWG. The decisive factor is the classification of the specific project.

Can the same heat pump be used in all three countries?

Technically, only if it can cover the calculated load at the design temperature and required temperature level for the specific location. Legally, requirements for installation, noise emissions, power connection, peak load, and other local regulations must be checked separately.

Is MuKEn 2025 legally binding throughout Switzerland?

No. They are model regulations intended for adoption by the cantons. The legally binding version is the one enacted by the specific canton, applicable at the project's location and at the time of the permit process.

When should the heating system provider be contacted?

Early in the process to discuss technical options, but an order should only be placed once the location, project classification, heating load, connected load, and the required regulatory approval path are fully clarified. This allows the provider to design the system based on reliable parameters.

Conclusion: In this air dome heating comparison DACH, the best air dome heating solution isn't determined by a specific energy source, but by following the correct process. For air dome heating systems Germany's GModG exemption provides a different starting point than Austria's EWG for sports hall heating Austria. For inflatable structure heating Switzerland, the cantonal regulations must be examined first. A robust project plan integrates written legal clarification, heating load, infrastructure, and life-cycle costs before the system is ordered.