Blog

Heating for Air Domes in Switzerland: MuKEn, Systems, and Approval

Heating for air domes in Switzerland at a modern membrane hall

Quick Answer: For an air dome in Switzerland, technically, a heat pump, a suitable district heating network, wood firing, or otherwise unusable waste heat are primarily suitable. However, the legal situation is cantonal. MuKEn 2025 are model provisions and not automatically applicable law in every canton. Therefore, before ordering and connecting to the grid, clarify in writing which cantonal regulations, EN-132 requirements, and approval procedures apply to the specific location.

A heating system for an air dome in Switzerland cannot be chosen based solely on the price of a heat generator. The system must deliver the calculated winter load, work with the hall's air distribution and pressure maintenance, be connectable at the site, and comply with the regulations of the competent canton.

The crucial difference from a nationwide uniform law: In Switzerland, according to Article 89, Paragraph 4 of the Federal Constitution, the cantons are primarily responsible for regulating energy consumption in buildings. The Conference of Cantonal Energy Directors (EnDK) develops common model provisions with MuKEn. However, these only become legally binding through cantonal legislation. At the same time, the model framework for heated air domes refers to the EN-132 recommendation of the Conference of Cantonal Energy Offices (EnFK).

This article is a planning guide, not legal advice, and not a project-specific building services design. Before ordering, submitting a building application, and installation, check the current cantonal legal situation and have the competent authorities confirm the requirements in writing.

Table of Contents

The Heating Decision in Five Steps

The safe sequence is: determine the canton, clarify the legal process, calculate the heating load, confirm infrastructure, and only then select the system. A technical offer without these fundamentals may be unusable for approval or too small for a cold winter day.

  1. Define Project and Location: Document canton, municipality, parcel, use, installation months, occupancy, hall geometry, anchoring, foundations, and permanent ancillary buildings.
  2. Identify Applicable Law: Do not just read MuKEn, but check the current energy law, ordinance, building regulations, and implementation guidelines of the canton where the project is located.
  3. Clarify Official Procedure in Writing: Ask the building permit authority and the cantonal energy office for classification, type of procedure, and a complete list of required proofs.
  4. Prove Technical Load and Connections: Calculate heating load, air volumes, and heating-up operation; the electricity grid operator or district heating supplier must confirm the available capacity.
  5. Compare Only Permissible Variants: Evaluate investment, connection, energy, capacity prices, maintenance, replacement, emissions, and operation over the same period.

Planning Principle: Heat source, warm air distribution, and support air are connected but not identical. A heat pump or district heating network can supply a heating coil in the air handling unit. Pressure maintenance and its safety functions must still be designed independently.

Why the Canton Decides for Air Domes

Switzerland does not have a single, nationwide identical set of regulations for every heated air dome. Article 89, Paragraph 4 of the Federal Constitution primarily assigns the regulation of energy consumption in buildings to the cantons. These enact their own energy and building laws, ordinances, and implementation requirements.

The EnDK coordinates these rules through the model provisions of the cantons in the energy sector. This creates a common framework, but not automatic uniformity. A canton can adopt a provision, adapt it, implement it later, or combine it with additional requirements. The responsibilities of the municipality, cantonal energy office, and building permit authority also differ.

For the project, this means: The name "air dome" is not enough. The authority requires the type of construction, duration of installation, use, temperature, anchoring, and technology. Only then can it assess which energy and building regulations apply, whether an energy certificate is required, and whether relaxations or an exceptional permit can even be considered.

MuKEn 2025: Guidance, but Not Automatically Applicable Law

MuKEn 2025 were adopted by the EnDK on August 29, 2025, and recommended to the cantons for adoption. The document states a goal of implementation by 2030. Until their respective cantonal entry into force, the requirements formulated therein remain model provisions.

For heated air domes, the following points in the model are particularly relevant:

These figures are not a nationwide approval: The 70-percent rule for district heating networks and the 100 kW/10-percent rule for peak load come from MuKEn 2025. They apply to a specific project only to the extent that the canton concerned has effectively adopted them. Do not order a hybrid system based on the model document alone.

MuKEn 2014 or 2025?

The question can only be answered cantonally and at the planned submission time. A project may still fall under cantonal law based on MuKEn 2014, already have to meet amended cantonal rules, or be planned during a transition phase. Therefore, check the consolidated version of the cantonal law and ordinance, as well as entry into force and transitional provisions.

What Role Does the EnFK Recommendation EN-132 Play?

EN-132 is a recommendation for heated air domes and the assessment of corresponding exceptional permits, not an independent nationwide law. The available edition dates from June 2017 and is materially identical to the December 2007 edition. Its legal significance arises particularly when a canton explicitly adopts it or uses it as an assessment standard.

The recommendation was developed because membrane halls often cannot meet the usual thermal insulation requirements of a conventional building envelope. In cases where an exceptional permit is considered, EN-132 mentions, among other things:

The historical calculation examples in EN-132 are not a guarantee for the current consumption of a CENTAURY+ hall and no substitute for a current project calculation. Membrane structure, geometry, climate, air exchange, target temperature, entrances, control, and usage profile change the result. Only project-specific inputs and a transparent calculation method are reliable.

Temporary or Seasonal Air Dome: No Automatic Exemption

"Seasonal," "mobile," or "provisional" does not automatically mean permit-free or exempt from energy regulations. Annual dismantling can be important for classification but does not replace a review of cantonal law.

Authorities may consider, among other things, the following characteristics:

MuKEn 2025 provides for possible exceptions for electric resistance heating in the model for certain provisional buildings erected for a maximum of three years. This, too, is not an automatic nationwide exception for every seasonal sports hall. The canton must have adopted the corresponding rule, and the competent authority must confirm that the specific project falls under it.

Heating Systems for Air Domes in Switzerland Compared

Heat pumps, suitable district heating networks, wood, and waste heat are the most robust starting points for a cantonal preliminary review. Whether they are technically and economically suitable depends on heating load, temperature level, connection capacity, location, logistics, and operating hours.

Heating Option Potential Advantage Technical Considerations Legal Confirmation Required
Air or Water Heat Pump Utilizes ambient heat and can supply a hot water coil or suitable air system Performance and efficiency at design temperature, defrosting, flow temperature, noise, peak load, and electrical connection Installation, noise, drilling or water extraction, and cantonal peak load concept
District Heating / Remote Heating Minimal generation technology at the hall, no on-site fuel storage Guaranteed capacity, flow and return temperatures, routing, connection costs, base and capacity charges Current cantonal origin or CO2 certificate; do not adopt MuKEn 2025 model limits unchecked
Wood Firing / Biomass Renewable fuel and high thermal output Storage, delivery, conveying, buffer, partial load, ash, chimney, and maintenance Air pollution control, fire protection, storage, exhaust gas, and building permit
Otherwise Unusable Waste Heat Utilization of a local energy source with low additional generation Temperature, capacity, availability, reserve, piping, property line, and contract Recognition as otherwise unusable waste heat and proof in the cantonal procedure
Direct Electric Resistance Heating Simple technology without fuel and exhaust gas Very high connection capacity, capacity charges, and operating costs Do not assume permissibility: clarify cantonal prohibition, emergency heating, and possible exceptions in writing
Gas, Oil, or Fossil Hybrid Peak High performance and fast response Connection/storage, exhaust gas, emissions, fire protection, CO2 and price risk No nationwide approval. Evaluate only according to applicable cantonal law and written project confirmation

Heat Pump: Do Not Dimension with Prospectus COP

For a large air dome, the actually available heating capacity on the cold design day is what matters. The characteristic values at local outdoor temperature and the required flow temperature are needed. Defrosting phases, simultaneous fan load, grid connection, noise, and the desired heating-up time after a setback must be included in the concept.

An annual performance factor does not answer whether the system covers the highest hourly load. If a second heat source is to cover the peak, its energy source must be cantonally permissible. A fossil boiler does not become permissible simply because it is only intended to run rarely.

District Heating Network: Check Origin and Capacity Separately

A connection can be legally suitable but technically too small or economically unfavorable. The supplier should confirm the energy mix or CO2 certificate, available capacity, temperatures, connection date, and complete price structure in writing. The 70-percent limit from MuKEn 2025 should only be applied if it applies to the project in the competent canton.

Wood and Waste Heat: The Overall System Counts

For wood firing, storage and delivery are as much a part of planning as the boiler, buffer, exhaust gas, and ash. For waste heat, availability and reserve are crucial: a source that is absent during the coldest operating hours requires a permissible backup. Both solutions must be integrated into the hall's warm air system and control.

Energy Efficiency: Membrane, Airtightness, and Control Before More Power

The best heat source does not compensate for unnecessary losses. In an air dome, membrane structure, connections, leakages, entrances, air exchange, operating pressure, and target temperature directly influence the heating load.

For a reliable comparison, all providers should use the same inputs:

EN-132 emphasizes airtight anchoring, careful penetrations, entrance airlocks, object-specific ventilation, and electronic control. These principles remain sensible for planning, even if historical U-values and consumption examples should not be transferred unchecked to a new product. Our overview of heating systems and heating costs explains the technical calculation in more detail.

Approval Process: From Location to Reliable Clearance

Start with a coordinated preliminary inquiry before ordering the heat generator. The EnDK centrally lists the cantonal energy laws, ordinances, and energy offices. For the building law route, the competent municipality or cantonal building authority must also be involved.

  1. Secure Applicable Enactments: Download current consolidated versions of the energy law, energy ordinance, building law, and relevant implementation guidelines of the canton.
  2. Create Project Folder: Document site plan, use, duration of installation, dimensions, membrane structure, anchoring, foundations, occupancy, entrances, technology, and neighborhood.
  3. Include Heating Concept: Present heating load, air volumes, target temperature, operating hours, heat source, capacity, peak load, installation location, noise, and exhaust gas or outdoor unit.
  4. Inquire About Classification: The authority should explain in writing how the hall and its heating are classified and whether and how EN-132 will be applied.
  5. Request Procedure List: Clarify building application, energy certificate, fire protection, air pollution control, noise, water protection, electrical connection, and other project-specific proofs.
  6. Have Supplier Confirm: Secure electricity or district heating capacity, connection conditions, deadline, energy mix, and tariffs in writing.
  7. Only Then Tender: Procure only variants that are compatible with the confirmed legal situation, infrastructure, and heating load.

Questions for the Cantonal Energy Office

  1. Which version of the cantonal energy legislation applies at the planned submission and construction time?
  2. Which MuKEn provisions has the canton actually adopted?
  3. Will the EnFK recommendation EN-132 be binding, noteworthy, or used as an assessment aid for this hall?
  4. Which heat generators and peak load solutions are permissible for the exact project?
  5. How must a district heating network prove its origin and quality?
  6. Is resistance or emergency heating permitted, and with what capacity and operating limit?
  7. What relaxations can be requested for a seasonal or provisional structure?
  8. Which forms, calculations, and expert proofs must be submitted?

The general planning of an air dome and the responsibilities in the procedure are additionally described in our guide to air dome planning permission.

Example Nidwalden: A Clear Cantonal Rule

Nidwalden shows why a cantonal review is indispensable. Its Cantonal Energy Ordinance has been in force since 2021; the current version explicitly refers to the EnFK recommendation EN-132 for heated air domes in § 17. Paragraph 3 requires that heat generation be carried out with renewable energies or otherwise unusable waste heat.

§ 21 also limits stationary electric resistance heating systems. Defined emergency heating and possible exceptions upon request are provided, among other things, for certain provisional buildings if another heating system is not possible, economically unreasonable, or disproportionate.

Limitation of the example: Nidwalden law does not automatically apply in Zurich, Bern, Geneva, or any other canton. The example merely proves that a canton can explicitly adopt EN-132 and enact additional clear requirements.

Common Mistakes When Heating an Air Dome in Switzerland

Frequently Asked Questions

What heating system is suitable for an air dome in Switzerland?

Technically, a properly designed heat pump, a suitable district heating network, wood firing, or otherwise unusable waste heat are primarily suitable. Which solution is legally permissible depends on the applicable law of the canton where the project is located, the project's classification, and the requirements of the approval authorities.

Are MuKEn 2025 binding in all cantons?

No. MuKEn 2025 are model provisions of the EnDK and have been recommended to the cantons for adoption. The energy and building legislation enacted in the respective canton is binding. Therefore, the current cantonal version must be checked before selecting a system.

What role does the EN-132 recommendation play?

EN-132 is a recommendation from the Conference of Cantonal Energy Offices for heated air domes and the assessment of corresponding exceptional permits. It is not a nationwide law in itself. However, a canton can explicitly refer to it, as Nidwalden does in its Energy Ordinance, for example.

Is direct electric resistance heating permitted?

A blanket nationwide answer is not possible. MuKEn 2025, as a model provision, generally prohibits new stationary electric resistance heating systems but allows for limited emergency heating and regulated exceptions. The cantonal implementation and the written assessment of the specific system are decisive.

Is a seasonal air dome automatically exempt from energy regulations?

No. Seasonal dismantling or designation as temporary does not create an automatic nationwide exemption. The duration of installation, anchoring, foundations, use, and cantonal building and energy law determine which permits, proofs, or relaxations apply.

What documents does the cantonal energy office require?

Helpful documents include the location and parcel, use, installation period, hall geometry, membrane structure, anchoring, target temperature, operating hours, heating load, air volumes, heat source, performance data, peak load concept, grid confirmations, and plans of the technical installations. The authority should confirm the project-specific list of documents in writing.

Sources

Limitation of this Guide: The article does not provide nationwide approval or rejection of any fuel and does not replace a cantonal legal review. Decisive factors are the location, submission date, cantonal enactments, project characteristics, and the written decision of the competent authorities.

Next Step: Cantonal Pre-Inquiry Before Equipment Selection

The best heating system is the solution that provides sufficient capacity at the site, is cantonally permissible, and is compatible with the air dome's envelope, air distribution, and operation. Start with the project folder and the cantonal preliminary inquiry. Then compare only confirmed variants on the same technical and economic basis.

Planning an air dome in Switzerland? Send CENTAURY+ the canton of location, dimensions, use, season, desired indoor temperature, anchoring concept, and available energy connections. We support technical preliminary planning; legal review, energy verification, and approval remain the tasks of the competent specialists and authorities.

← Back to Blog